Greenfield (TIPPY DAM - TAP144737)

Greenfield

Manistee County, Michigan · PJM

DC Readiness
59.8
Good / 100

Greenfield (TIPPY DAM - TAP144737) is a greenfield datacenter candidate site in Manistee County, Michigan, interconnecting through PJM. It screens at 59.8/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 2.2 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTIPPY DAM
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_ATSI
Wholesale LMP$42.97/MWh
Utility commercial rate0.10¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth11
Avg queue wait2.2 yrs
Recent queue wait2.2 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXPEthoplex Edge DC - Green Bay
IXP distance99.3 mi
Fiber providers5
Fiber coverage22.1%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance181.8 mi

Site characteristics

Site typeGreenfield
Parcel ownerWOLVERINE POWER SUPPLY COOP
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous

Risk & environment

Flood zoneZone X
Water stress (WRI)0.30
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score75/100
Construction cost index65.7 (avg 100)

Location context

Nearest datacenterEthoplex Edge DC - Green Bay
DC distance99.3 mi
Nearest rail10.4 mi
Nearest gas pipeline8.5 mi
Nearest fiber route63.1 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity10.35¢/kWh
Industrial electricity7.12¢/kWh
Cooling degree days700
Heating degree days6,600
Land price / acre$4,308

Incentive detail: Personal property tax exemption for eligible DC equipment; MEGA tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
56
Fiber connectivity12%
49
Energy cost10%
81
Water risk8%
91
Natural hazard8%
75
Buildability7%
80
Labor market4%
50
DC cluster4%
25
Land / acreage3%
48
Construction cost3%
95
Gas pipeline2%
73
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Manistee County, ranked by DC Readiness.

Sites near Greenfield (TIPPY DAM - TAP144737)
SiteTypeVoltageCapacityQueue waitScore
TES FILER CITY STATIONSubstation-Adjacent138 kV100 MW1.4 yrs68.9
UNKNOWN128881Substation-Adjacent138 kV100 MW2.2 yrs66.6
UNKNOWN133164Substation-Adjacent138 kV100 MW1.4 yrs62.4
EC Near TES Filer City StationGreenfield2.2 yrs60.8
EC Near TES Filer City StationGreenfield2.2 yrs60.6
EC Near TES Filer City StationGreenfield2.2 yrs60.5
Greenfield (KEYSTONE - LUDINGTON)Greenfield345 kV600 MW1.4 yrs60.2
EC Near TES Filer City StationGreenfield2.2 yrs60.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (TIPPY DAM - TAP144737), Manistee County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.