Greenfield (UNKNOWN128594 - TAP137410)

Greenfield

Hillsdale County, Michigan · PJM

DC Readiness
59.3
Good / 100

Greenfield (UNKNOWN128594 - TAP137410) is a greenfield datacenter candidate site in Hillsdale County, Michigan, interconnecting through PJM. It screens at 59.3/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 2.2 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN128594
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_ATSI
Wholesale LMP$42.97/MWh
Utility commercial rate0.10¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth11
Avg queue wait2.2 yrs
Recent queue wait2.2 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXPSynergy Fiber
IXP distance40.5 mi
Fiber providers9
Fiber coverage21.9%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance152.7 mi

Site characteristics

Site typeGreenfield
Parcel ownerCONSUMERS ENERGY CO
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Flood zoneZone X
Water stress (WRI)0.30
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score75/100
Construction cost index64.6 (avg 100)

Location context

Nearest datacenterDatacenter 11815482844
DC distance39.6 mi
Nearest rail12.5 mi
Nearest gas pipeline14.0 mi
Nearest fiber route175.4 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity9.60¢/kWh
Industrial electricity4.56¢/kWh
Cooling degree days700
Heating degree days6,600
Land price / acre$5,493

Incentive detail: Personal property tax exemption for eligible DC equipment; MEGA tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
56
Fiber connectivity12%
48
Energy cost10%
82
Water risk8%
94
Natural hazard8%
75
Buildability7%
65
Labor market4%
50
DC cluster4%
45
Land / acreage3%
46
Construction cost3%
96
Gas pipeline2%
55
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Hillsdale County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN128594 - TAP137410)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN128594Substation-Adjacent138 kV100 MW2.2 yrs65.3
ENDICOTT STATIONSubstation-Adjacent138 kV100 MW2.2 yrs62.7
OZ HillsdaleGreenfield2.2 yrs61.1
EC Coal Hillsdale CountyGreenfield2.2 yrs61.0
Greenfield (ENDICOTT STATION - UNKNOWN1285)Greenfield138 kV100 MW2.2 yrs60.2
Greenfield (ENDICOTT STATION - UNKNOWN1456)Greenfield138 kV100 MW2.2 yrs60.1
EC Coal Hillsdale CountyGreenfield2.2 yrs60.0
EC Near HillsdaleGreenfield2.2 yrs59.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN128594 - TAP137410), Hillsdale County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.