Greenfield (UNKNOWN111872 - SOUTHWEST SHRE)

Greenfield

De Soto Parish, Louisiana · ERCOT

DC Readiness
61.0
Good / 100

Greenfield (UNKNOWN111872 - SOUTHWEST SHRE) is a greenfield datacenter candidate site in De Soto Parish, Louisiana, interconnecting through ERCOT. It screens at 61.0/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 3.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN111872
Substation voltage345 kV
Available capacity600 MW
LMP zoneERCOT_CENTRAL
Wholesale LMP$18.75/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionERCOT
Queue depth876
Avg queue wait3.4 yrs
Recent queue wait3.1 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Nearest IXPDartPoints Shreveport, LA - SHV1
IXP distance17.3 mi
Fiber providers5
Fiber coverage7.9%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance174.3 mi

Site characteristics

Site typeGreenfield
Parcel ownerSOUTHWESTERN ELECTRIC POWER CO
Land owner typeprivate
Buildability15.0/100
Land cover (NLCD)Woody Wetlands

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score42/100
Construction cost index85.1 (avg 100)

Location context

Nearest datacenterDartPoints Shreveport, LA - SHV1
DC distance17.3 mi
Nearest rail0.1 mi
Nearest gas pipeline0.7 mi
Nearest fiber route11.9 mi
County hazard (FEMA NRI)Very High (58)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.94¢/kWh
Industrial electricity8.05¢/kWh
Cooling degree days2,700
Heating degree days1,700
Land price / acre$3,577

Incentive detail: Industrial Tax Exemption Program (ITEP) up to 80% property tax abatement for 10 years.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
55
Fiber connectivity12%
64
Energy cost10%
92
Water risk8%
89
Natural hazard8%
42
Buildability7%
15
Labor market4%
50
DC cluster4%
65
Land / acreage3%
50
Construction cost3%
79
Gas pipeline2%
98
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in De Soto Parish, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN111872 - SOUTHWEST SHRE)
SiteTypeVoltageCapacityQueue waitScore
Dolet HillsBrownfield721 MW71.4
WALLACE LAKESubstation-Adjacent138 kV100 MW3.4 yrs67.5
UNKNOWN112571Substation-Adjacent230 kV300 MW3.4 yrs66.2
UNKNOWN112570Substation-Adjacent230 kV300 MW3.4 yrs62.3
UNKNOWN111872Substation-Adjacent345 kV600 MW3.4 yrs59.6
EC Near Dolet HillsGreenfield1.4 yrs57.1
EC Coal De Soto ParishGreenfield1.4 yrs57.1
EC Coal De Soto ParishGreenfield1.4 yrs56.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN111872 - SOUTHWEST SHRE), De Soto Parish. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.