Greenfield (EUGENE - DEQUINE)

Greenfield

WARREN, Indiana · PJM

DC Readiness
65.4
Good / 100

Greenfield (EUGENE - DEQUINE) is a greenfield datacenter candidate site in WARREN, Indiana, interconnecting through PJM. It screens at 65.4/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 4.6 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationEUGENE
Substation voltage345 kV
Available capacity600 MW
LMP zonePJM_COMED
Wholesale LMP$33.95/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth265
Avg queue wait4.6 yrs
Recent queue wait2.9 yrs
Completion rate21%
Withdrawal rate79%

Connectivity

Nearest IXPWintek Corporation
IXP distance17.4 mi
Fiber providers4
Fiber coverage22.1%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance110.1 mi

Site characteristics

Site typeGreenfield
Parcel ownerDUKE ENERGY INDIANA INC
Land owner typeprivate
Buildability75.0/100
Land cover (NLCD)Pasture/Hay

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score68/100
Construction cost index75.4 (avg 100)

Location context

Nearest datacenterAgricultural and Biological Engineering
DC distance16.2 mi
Nearest rail2.1 mi
Nearest gas pipeline24.4 mi
Nearest fiber route64.8 mi
County hazard (FEMA NRI)Relatively Moderate (32)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.11¢/kWh
Industrial electricity7.99¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$7,338

Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
44
Fiber connectivity12%
66
Energy cost10%
87
Water risk8%
90
Natural hazard8%
68
Buildability7%
75
Labor market4%
50
DC cluster4%
65
Land / acreage3%
43
Construction cost3%
87
Gas pipeline2%
21
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in WARREN, ranked by DC Readiness.

Sites near Greenfield (EUGENE - DEQUINE)
SiteTypeVoltageCapacityQueue waitScore
Greenfield (BREED - DEQUINE)Greenfield345 kV600 MW4.6 yrs65.6
Greenfield (BREED - DEQUINE)Greenfield345 kV600 MW4.6 yrs64.6
Greenfield (ATTICA 230KV SUBSTATION - LAFA)Greenfield230 kV300 MW4.6 yrs64.2
EC Coal Warren CountyGreenfield3.0 yrs56.3
HOSE TECHNOLOGY, INC., DIVISION OF KURI (ALL OTHER MISCELLANEOUS FABRICATED METAL PRODUCT MANUFACTURING)Manufacturing51.5
ACCUBURN WILLIAMSPORT, INC. (IRON AND STEEL MILLS)Manufacturing51.1
S A L, INC. (MEAT PROCESSED FROM CARCASSES)Manufacturing51.0
TMF CENTER, INC. (MACHINE SHOPS)Manufacturing51.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (EUGENE - DEQUINE), WARREN. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.