Lemhi County, Idaho · SPP

DC Readiness
58.8
Good / 100

TAP207221 is a substation-adjacent datacenter candidate site in Lemhi County, Idaho, interconnecting through SPP. It screens at 58.8/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.1 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP207221
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth1
Avg queue wait1.1 yrs
Recent queue wait0.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPiConnect Missoula
IXP distance115.0 mi
Fiber providers1
Fiber coverage21.2%
Nearest cloud providerAzure
Nearest cloud regionwestus2
Cloud region distance307.0 mi

Site characteristics

Parcel ownerIDAHO POWER CO
Land owner typeprivate
Buildability40.0/100
Land cover (NLCD)Evergreen Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)2.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteMERIDIAN GOLD BEARTRACK MINE
Hazard sub-score75/100
Construction cost index64.4 (avg 100)

Location context

Nearest datacenterDatacenter 758426349
DC distance87.5 mi
Nearest rail3.8 mi
Nearest gas pipeline68.5 mi
Nearest fiber route34.7 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity8.81¢/kWh
Industrial electricity7.52¢/kWh
Cooling degree days500
Heating degree days6,400
Land price / acre$3,947

Incentive detail: Personal property tax exemption on computer equipment.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
76
Fiber connectivity12%
28
Energy cost10%
91
Water risk8%
47
Natural hazard8%
75
Buildability7%
40
Labor market4%
50
DC cluster4%
20
Land / acreage3%
49
Construction cost3%
96
Gas pipeline2%
0
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Lemhi County, ranked by DC Readiness.

Sites near TAP207221
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN201303Substation-Adjacent115 kV100 MW1.1 yrs63.5
UNKNOWN207232Substation-Adjacent115 kV100 MW1.1 yrs62.3
TAP207230Substation-Adjacent115 kV100 MW1.1 yrs62.0
UNKNOWN207234Substation-Adjacent115 kV100 MW1.1 yrs61.2
TAP207223Substation-Adjacent115 kV100 MW1.1 yrs60.7
TAP207227Substation-Adjacent115 kV100 MW1.1 yrs60.7
TAP207233Substation-Adjacent115 kV100 MW1.1 yrs59.9
UNKNOWN207224Substation-Adjacent115 kV100 MW1.1 yrs59.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP207221, Lemhi County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.