Greenfield (BIG GRASSY - UNKNOWN201598)

Greenfield

Clark County, Idaho · SPP

DC Readiness
61.0
Good / 100

Greenfield (BIG GRASSY - UNKNOWN201598) is a greenfield datacenter candidate site in Clark County, Idaho, interconnecting through SPP. It screens at 61.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.1 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationBIG GRASSY
Substation voltage115 kV
Available capacity100 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth1
Avg queue wait1.1 yrs
Recent queue wait0.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPMontana Opticom
IXP distance119.5 mi
Fiber providers2
Fiber coverage67.1%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance230.5 mi

Site characteristics

Site typeGreenfield
Parcel ownerPACIFICORP
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Flood zoneZone X
Water stress (WRI)2.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score85/100
Construction cost index86.6 (avg 100)

Location context

Nearest datacenterVentureData
DC distance26.7 mi
Nearest rail2.4 mi
Nearest gas pipeline76.8 mi
Nearest fiber route128.8 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity9.43¢/kWh
Industrial electricity8.29¢/kWh
Cooling degree days500
Heating degree days6,400
Land price / acre$3,102

Incentive detail: Personal property tax exemption on computer equipment.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
28
Speed to power15%
76
Fiber connectivity12%
66
Energy cost10%
90
Water risk8%
44
Natural hazard8%
85
Buildability7%
65
Labor market4%
50
DC cluster4%
60
Land / acreage3%
51
Construction cost3%
78
Gas pipeline2%
0
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Clark County, ranked by DC Readiness.

Sites near Greenfield (BIG GRASSY - UNKNOWN201598)
SiteTypeVoltageCapacityQueue waitScore
AMPSSubstation-Adjacent230 kV300 MW1.1 yrs70.8
Greenfield (MILL CREEK GENERATING STATION )Greenfield230 kV300 MW1.1 yrs64.6
Greenfield (MILL CREEK GENERATING STATION )Greenfield230 kV300 MW1.1 yrs64.5
Greenfield (MILL CREEK GENERATING STATION )Greenfield230 kV300 MW1.1 yrs63.8
Greenfield (MILL CREEK GENERATING STATION )Greenfield230 kV300 MW1.1 yrs63.2
Greenfield (MILL CREEK GENERATING STATION )Greenfield230 kV300 MW1.1 yrs62.6
Greenfield (BIG GRASSY - UNKNOWN201598)Greenfield115 kV100 MW1.1 yrs62.5
Greenfield (BIG GRASSY - UNKNOWN201598)Greenfield115 kV100 MW1.1 yrs62.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (BIG GRASSY - UNKNOWN201598), Clark County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.