Greenfield (GOSHEN - TAP204802)

Greenfield

Bingham County, Idaho · WECC

DC Readiness
59.2
Good / 100

Greenfield (GOSHEN - TAP204802) is a greenfield datacenter candidate site in Bingham County, Idaho, interconnecting through WECC. It screens at 59.2/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 2.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationGOSHEN
Substation voltage161 kV
Available capacity100 MW
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait2.0 yrs
Recent queue wait1.9 yrs
Completion rate30%
Withdrawal rate70%

Connectivity

Fiber providers8
Fiber coverage52.9%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance179.9 mi

Site characteristics

Site typeGreenfield
Parcel ownerStolworthy Brent Family
Parcel APNRP0381400
Land owner typeprivate
Buildability90.0/100
Land cover (NLCD)Developed, Open Space

Risk & environment

Flood zoneZone X
Water stress (WRI)2.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score85/100
Construction cost index65.1 (avg 100)

Location context

Nearest datacenterVentureData
DC distance39.6 mi
Nearest rail3.7 mi
Nearest gas pipeline34.7 mi
Nearest fiber route172.5 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity9.34¢/kWh
Industrial electricity7.93¢/kWh
Cooling degree days500
Heating degree days6,400
Land price / acre$3,789

Incentive detail: Personal property tax exemption on computer equipment.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
32
Speed to power15%
42
Fiber connectivity12%
65
Energy cost10%
100
Water risk8%
44
Natural hazard8%
85
Buildability7%
90
Labor market4%
50
DC cluster4%
45
Land / acreage3%
49
Construction cost3%
96
Gas pipeline2%
0
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Bingham County, ranked by DC Readiness.

Sites near Greenfield (GOSHEN - TAP204802)
SiteTypeVoltageCapacityQueue waitScore
GOSHENSubstation-Adjacent345 kV600 MW2.0 yrs69.7
PINGREESubstation-Adjacent138 kV100 MW2.0 yrs66.8
TAP204775Substation-Adjacent138 kV100 MW2.0 yrs66.6
TAP204750Substation-Adjacent138 kV100 MW2.0 yrs66.6
TAP204776Substation-Adjacent138 kV100 MW2.0 yrs66.5
TYHEESubstation-Adjacent138 kV100 MW2.0 yrs66.5
TAP204751Substation-Adjacent138 kV100 MW2.0 yrs66.5
FORT HALLSubstation-Adjacent138 kV100 MW2.0 yrs66.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (GOSHEN - TAP204802), Bingham County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.