Greenfield (THOMSON PRIMARY - VOGTLE) is a greenfield datacenter candidate site in Glascock County, Georgia, interconnecting through SERC. It screens at 71.0/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 3.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTHOMSON PRIMARY
Substation voltage500 kV
Available capacity1,000 MW
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait3.7 yrs
Recent queue wait3.5 yrs
Completion rate15%
Withdrawal rate85%

Connectivity

Nearest IXPT5@Augusta
IXP distance17.4 mi
Fiber providers3
Fiber coverage36.8%
Nearest cloud providerGCP
Nearest cloud regionus-east1
Cloud region distance139.2 mi

Site characteristics

Site typeGreenfield
Parcel ownerGEORGIA POWER CO
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous

Risk & environment

Flood zoneZone X
Water stress (WRI)1.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score60/100
Construction cost index90.7 (avg 100)

Location context

Nearest datacenterT5@Augusta
DC distance17.4 mi
Nearest rail2.5 mi
Nearest gas pipeline5.7 mi
Nearest fiber route117.8 mi
County hazard (FEMA NRI)Relatively High (40)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.17¢/kWh
Industrial electricity7.52¢/kWh
Cooling degree days2,200
Heating degree days2,400
Land price / acre$2,364

Incentive detail: Sales tax exemption on data processing equipment; investment tax credits for $150M+ projects.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
72
Speed to power15%
68
Fiber connectivity12%
69
Energy cost10%
91
Water risk8%
80
Natural hazard8%
60
Buildability7%
80
Labor market4%
50
DC cluster4%
65
Land / acreage3%
52
Construction cost3%
74
Gas pipeline2%
82
Tax incentive2%
100
Climate / cooling2%
15

Nearby comparable sites

Other scored datacenter candidate sites in Glascock County, ranked by DC Readiness.

Sites near Greenfield (THOMSON PRIMARY - VOGTLE)
SiteTypeVoltageCapacityQueue waitScore
Greenfield (THOMSON PRIMARY - WARTHEN SUBS)Greenfield500 kV1,000 MW3.7 yrs69.6
Greenfield (THOMSON PRIMARY - WARTHEN SUBS)Greenfield500 kV1,000 MW3.7 yrs69.0
Greenfield (THOMSON PRIMARY - WARTHEN SUBS)Greenfield500 kV1,000 MW3.7 yrs68.7
THOMSON PRIMARYSubstation-Adjacent500 kV1,000 MW3.7 yrs68.6
WARTHEN SUBSTATIONSubstation-Adjacent500 kV1,000 MW3.7 yrs68.5
Greenfield (THOMSON PRIMARY - WARTHEN SUBS)Greenfield500 kV1,000 MW3.7 yrs68.4
Greenfield (UNKNOWN113403 - HARLLEE BRANCH)Greenfield230 kV300 MW3.7 yrs64.9
Greenfield (UNKNOWN113403 - HARLLEE BRANCH)Greenfield230 kV300 MW3.7 yrs64.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (THOMSON PRIMARY - VOGTLE), Glascock County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.