Greenfield (UNKNOWN107674 - LIVE OAK)

Greenfield

Suwannee, Florida · SERC

DC Readiness
56.5
Good / 100

Greenfield (UNKNOWN107674 - LIVE OAK) is a greenfield datacenter candidate site in Suwannee, Florida, interconnecting through SERC. It screens at 56.5/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 5.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN107674
Substation voltage115 kV
Available capacity100 MW
Utility commercial rate0.13¢/kWh

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait5.8 yrs
Recent queue wait5.2 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPCologix JAX1
IXP distance80.2 mi
Fiber providers5
Fiber coverage78.0%
Nearest cloud providerGCP
Nearest cloud regionus-east1
Cloud region distance265.4 mi

Site characteristics

Site typeGreenfield
Parcel ownerDUKE ENERGY FLORIDA, LLC
Land owner typeprivate
Buildability40.0/100
Land cover (NLCD)Evergreen Forest

Risk & environment

Flood zoneZone AE (SFHA)
Water stress (WRI)1.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteSLOAN CONSTRUCTION CO INC
Hazard sub-score20/100
Construction cost index71.2 (avg 100)

Location context

Nearest datacenterHiPerGator
DC distance61.5 mi
Nearest rail1.0 mi
Nearest gas pipeline0.1 mi
Nearest fiber route133.2 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.78¢/kWh
Industrial electricity7.83¢/kWh
Cooling degree days3,500
Heating degree days700
Land price / acre$6,499

Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
28
Speed to power15%
70
Fiber connectivity12%
71
Energy cost10%
89
Water risk8%
83
Natural hazard8%
20
Buildability7%
40
Labor market4%
50
DC cluster4%
40
Land / acreage3%
53
Construction cost3%
91
Gas pipeline2%
100
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in Suwannee, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN107674 - LIVE OAK)
SiteTypeVoltageCapacityQueue waitScore
FORT WHITESubstation-Adjacent230 kV300 MW5.8 yrs70.0
UNKNOWN107674Substation-Adjacent230 kV300 MW5.8 yrs68.8
Suwannee RiverBrownfield147 MW68.3
UNKNOWN107675Substation-Adjacent115 kV100 MW3.6 yrs66.6
UNKNOWN121132Substation-Adjacent115 kV100 MW3.6 yrs65.9
TAP174787Substation-Adjacent115 kV100 MW3.6 yrs64.8
UNKNOWN121131Substation-Adjacent115 kV100 MW3.6 yrs64.5
Greenfield (UNKNOWN107674 - FORT WHITE)Greenfield230 kV300 MW5.8 yrs62.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN107674 - LIVE OAK), Suwannee. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.