Greenfield (HUMBOLDT - TRINITY) is a greenfield datacenter candidate site in Trinity County, California, interconnecting through CAISO. It screens at 41.8/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 5.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationHUMBOLDT
Substation voltage115 kV
Available capacity100 MW
LMP zoneCAISO_NP15
Wholesale LMP$16.53/MWh
Utility commercial rate0.28¢/kWh

Speed to power

ISO / RTO regionCAISO
Queue depth311
Avg queue wait5.7 yrs
Recent queue wait3.0 yrs
Completion rate11%
Withdrawal rate89%

Connectivity

Nearest IXPData Center West Medford
IXP distance110.9 mi
Fiber providers1
Fiber coverage22.8%
Nearest cloud providerAzure
Nearest cloud regionwestus
Cloud region distance206.5 mi

Site characteristics

Site typeGreenfield
Parcel ownerTRINITY PUBLIC UTILITIES DISTRICT
Land owner typeprivate
Buildability50.0/100

Risk & environment

Flood zoneZone X
Water stress (WRI)3.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteJUNCTION CITY TRANSFER STATION
Hazard sub-score42/100
Construction cost index103.4 (avg 100)

Location context

Nearest datacenterData Center West Medford
DC distance110.9 mi
Nearest rail2.9 mi
Nearest gas pipeline14.5 mi
Nearest fiber route141.0 mi
County hazard (FEMA NRI)Relatively High (48)
DC tax incentiveNo
Commercial electricity27.79¢/kWh
Industrial electricity21.50¢/kWh
Cooling degree days1,000
Heating degree days2,500
Land price / acre$2,661

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
28
Speed to power15%
35
Fiber connectivity12%
53
Energy cost10%
52
Water risk8%
47
Natural hazard8%
42
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
51
Construction cost3%
64
Gas pipeline2%
53
Tax incentive2%
0
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Trinity County, ranked by DC Readiness.

Sites near Greenfield (HUMBOLDT - TRINITY)
SiteTypeVoltageCapacityQueue waitScore
TRINITYSubstation-Adjacent230 kV300 MW5.7 yrs53.7
CARRSubstation-Adjacent230 kV300 MW5.7 yrs53.0
WEAVERVILLESubstation-Adjacent115 kV100 MW5.7 yrs49.2
DOUGLAS CITYSubstation-Adjacent115 kV100 MW5.7 yrs48.5
Greenfield (COTTONWOOD - BRIDGEVILLE)Greenfield115 kV100 MW5.7 yrs46.5
LEWISTONSubstation-Adjacent115 kV100 MW5.7 yrs46.4
Greenfield (COTTONWOOD - BRIDGEVILLE)Greenfield115 kV100 MW5.7 yrs45.8
Greenfield (COTTONWOOD - BRIDGEVILLE)Greenfield115 kV100 MW5.7 yrs45.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.