GREENLAND GAP

Substation

West Virginia · THE POTOMAC EDISON CO

Max voltage
500
kV

GREENLAND GAP is an electric transmission substation in West Virginia, operated by THE POTOMAC EDISON CO. It is classified as extra-high-voltage (500 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage500 kV
Min voltage500 kV
Voltage classExtra-high-voltage (500 kV)
Connected lines3

Ownership & operation

OperatorTHE POTOMAC EDISON CO
Coordinates39.1541, -78.8991

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#6903500 kVTHE POTOMAC EDISON COIN SERVICE56.1 mi
#33859500 kVTHE POTOMAC EDISON COIN SERVICE3.3 mi
#64063500 kVTHE POTOMAC EDISON CO0.2 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of GREENLAND GAP, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near GREENLAND GAP substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
DOUBSSubstation-AdjacentWVHampshire County500 kV1,000 MW3.0 yrs72.8
BLACK OAKSubstation-AdjacentMDAllegany County500 kV1,000 MW3.0 yrs71.9
MOUNT STORMSubstation-AdjacentWVGrant County500 kV1,000 MW3.0 yrs71.2
VALLEYSubstation-AdjacentWVPendleton County500 kV1,000 MW3.0 yrs69.9
Greenfield (DOUBS - NEW CREEK WIND)GreenfieldWVHampshire County500 kV1,000 MW3.0 yrs69.4
Greenfield (BLACK OAK - BEDINGTON)GreenfieldWVHampshire County500 kV1,000 MW3.0 yrs68.7
Greenfield (MOUNT STORM - MEADOW BROOK)GreenfieldWVHampshire County500 kV1,000 MW3.0 yrs68.6
Greenfield (MOUNT STORM - MEADOW BROOK)GreenfieldWVHardy County500 kV1,000 MW3.0 yrs68.1

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen