WEST POINT

Substation

Virginia · VIRGINIA ELECTRIC & POWER CO

Max voltage
230
kV

WEST POINT is an electric transmission substation in Virginia, operated by VIRGINIA ELECTRIC & POWER CO. It is classified as high-voltage (230 kv) and connects 2 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage230 kV
Min voltage230 kV
Voltage classHigh-voltage (230 kV)
Connected lines2

Ownership & operation

OperatorVIRGINIA ELECTRIC & POWER CO
Coordinates37.5453, -76.8098

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#14619230 kVVIRGINIA ELECTRIC & POWER COIN SERVICE1.1 mi
#64990230 kVVIRGINIA ELECTRIC & POWER CO0.1 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of WEST POINT, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near WEST POINT substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
Greenfield (ELMONT - CHICKAHOMINY)GreenfieldVAHenrico County500 kV1,000 MW3.1 yrs75.3
CHICKAHOMINYSubstation-AdjacentVACharles City County500 kV1,000 MW3.1 yrs72.4
FORT EUSTISSubstation-AdjacentVANewport News city230 kV300 MW3.1 yrs72.0
Greenfield (CHICKAHOMINY - SURRY)GreenfieldVASurry County500 kV1,000 MW3.1 yrs70.6
TAP147954Substation-AdjacentVANewport News city230 kV300 MW3.1 yrs70.5
UNKNOWN114847Substation-AdjacentVANew Kent County230 kV300 MW3.1 yrs70.4
Greenfield (CHICKAHOMINY - SURRY)GreenfieldVASurry County500 kV1,000 MW3.1 yrs69.9
UNKNOWN114845Substation-AdjacentVAWilliamsburg city230 kV300 MW3.1 yrs69.6

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen