TAP148055

Substation

Virginia · DUKE ENERGY PROGRESS - (NC)

Max voltage
115
kV

TAP148055 is an electric transmission substation in Virginia, operated by DUKE ENERGY PROGRESS - (NC). It is classified as sub-transmission (115 kv) and connects 1 transmission line. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines1

Ownership & operation

OperatorDUKE ENERGY PROGRESS - (NC)
Coordinates36.5128, -78.0443

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#19399115 kVDUKE ENERGY PROGRESS - (NC)IN SERVICE15.6 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP148055, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP148055 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN111421Substation-AdjacentVAGreensville County230 kV300 MW3.1 yrs70.4
Greenfield (CLOVER - UNKNOWN175464)GreenfieldVALunenburg County500 kV1,000 MW3.1 yrs69.5
KERR DAMSubstation-AdjacentVAMecklenburg County115 kV100 MW3.1 yrs69.3
Greenfield (CLOVER - UNKNOWN175464)GreenfieldVALunenburg County500 kV1,000 MW3.1 yrs69.0
Greenfield (CLOVER - UNKNOWN175464)GreenfieldVALunenburg County500 kV1,000 MW3.1 yrs68.6
Greenfield (WAKE - CARSON)GreenfieldVAGreensville County500 kV1,000 MW3.1 yrs68.4
BEECHWOOD DPSubstation-AdjacentVAMecklenburg County115 kV100 MW3.1 yrs68.1
SOUTH HILLSubstation-AdjacentVAMecklenburg County115 kV100 MW3.1 yrs67.9

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP148055 substation, Virginia. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.