TAP305427

Substation

Texas · ONCOR ELECTRIC DELIVERY CO.

Max voltage
138
kV

TAP305427 is an electric transmission substation in Texas, operated by ONCOR ELECTRIC DELIVERY CO.. It is classified as sub-transmission (138 kv) and connects 1 transmission line. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage138 kV
Min voltage138 kV
Voltage classSub-transmission (138 kV)
Connected lines1

Ownership & operation

OperatorONCOR ELECTRIC DELIVERY CO.
StateTexas
Coordinates31.4249, -97.3799

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#85628138 kVONCOR ELECTRIC DELIVERY CO.5.7 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP305427, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP305427 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
Lake CreekBrownfieldTXMcLennan1,357 MW73.1
LAKE CREEKSubstation-AdjacentTXMcLennan County345 kV600 MW3.4 yrs72.8
ELM MOTT 345Substation-AdjacentTXMcLennan County345 kV600 MW3.4 yrs72.4
UNKNOWN306704Substation-AdjacentTXMcLennan County345 kV600 MW3.4 yrs70.7
TEMPLE PECAN CREEKSubstation-AdjacentTXBell County345 kV600 MW3.4 yrs70.2
KILLEENSubstation-AdjacentTXBell County345 kV600 MW3.4 yrs69.8
UNKNOWN301533Substation-AdjacentTXBell County345 kV600 MW3.4 yrs69.2
UNKNOWN301218Substation-AdjacentTXMcLennan County161 kV100 MW3.4 yrs68.6

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP305427 substation, Texas. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.