Bell County, Texas · ERCOT

DC Readiness
69.8
Good / 100

KILLEEN is a substation-adjacent datacenter candidate site in Bell County, Texas, interconnecting through ERCOT. It screens at 69.8/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 3.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationKILLEEN
Substation distance0.0 mi
Substation voltage345 kV
Available capacity600 MW
LMP zoneERCOT_CENTRAL
Wholesale LMP$18.75/MWh
Utility commercial rate0.15¢/kWh

Speed to power

ISO / RTO regionERCOT
Queue depth876
Avg queue wait3.4 yrs
Recent queue wait3.1 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Nearest IXPDataBank Austin (AUS1)
IXP distance41.7 mi
Fiber providers14
Fiber coverage66.0%
Nearest cloud providerAzure
Nearest cloud regionsouthcentralus
Cloud region distance121.3 mi

Site characteristics

Parcel ownerONCOR ELECTRIC DELIVERY CO.
Land owner typeprivate
Buildability95.0/100
Land cover (NLCD)Developed, Medium Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)2.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score45/100
Construction cost index89.9 (avg 100)

Location context

Nearest datacenterDataBank Austin (AUS1)
DC distance41.7 mi
Nearest rail5.3 mi
Nearest gas pipeline5.6 mi
Nearest fiber route136.0 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity14.72¢/kWh
Industrial electricity5.66¢/kWh
Cooling degree days2,600
Heating degree days1,800
Land price / acre$4,587

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
87
Speed to power15%
59
Fiber connectivity12%
64
Energy cost10%
91
Water risk8%
62
Natural hazard8%
45
Buildability7%
95
Labor market4%
50
DC cluster4%
45
Land / acreage3%
63
Construction cost3%
75
Gas pipeline2%
82
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in Bell County, ranked by DC Readiness.

Sites near KILLEEN
SiteTypeVoltageCapacityQueue waitScore
TEMPLE PECAN CREEKSubstation-Adjacent345 kV600 MW3.4 yrs70.2
UNKNOWN301533Substation-Adjacent345 kV600 MW3.4 yrs69.2
UNKNOWN307653Substation-Adjacent345 kV600 MW3.4 yrs67.9
TEMPLE SWITCHINGSubstation-Adjacent345 kV600 MW3.4 yrs67.2
UNKNOWN309671Substation-Adjacent138 kV100 MW3.4 yrs63.9
UNKNOWN306554Substation-Adjacent138 kV100 MW3.4 yrs63.8
UNKNOWN308182Substation-Adjacent138 kV100 MW3.4 yrs63.6
UNKNOWN301764Substation-Adjacent138 kV100 MW3.4 yrs63.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen