TAP155278 is an electric transmission substation in Tennessee, operated by TENNESSEE VALLEY AUTHORITY. It is classified as sub-transmission (138 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #3093 | 161 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 0.1 mi |
| #28263 | 161 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 2.2 mi |
| #45688 | 161 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 5.1 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of TAP155278, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| RUTHERFORD | Substation-Adjacent | TN | Williamson County | 500 kV | 1,000 MW | 3.7 yrs | 76.5 |
| MAURY | Substation-Adjacent | TN | Maury County | 500 kV | 1,000 MW | 3.7 yrs | 76.4 |
| Greenfield (PIN HOOK - DAVIDSON) | Greenfield | TN | Williamson County | 500 kV | 1,000 MW | 3.7 yrs | 75.9 |
| CANE RIDGE | Substation-Adjacent | TN | Davidson County | 161 kV | 100 MW | 3.7 yrs | 75.1 |
| ELYSLAN | Substation-Adjacent | TN | Davidson County | 161 kV | 100 MW | 3.7 yrs | 74.7 |
| TAP152207 | Substation-Adjacent | TN | Davidson County | 161 kV | 100 MW | 3.7 yrs | 74.6 |
| PIN HOOK | Substation-Adjacent | TN | Davidson County | 500 kV | 1,000 MW | 3.7 yrs | 74.3 |
| Greenfield (RUTHERFORD - MAURY) | Greenfield | TN | Williamson County | 500 kV | 1,000 MW | 3.7 yrs | 74.3 |
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for TAP155278 substation, Tennessee. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.