Greenfield (PIN HOOK - DAVIDSON)

Greenfield

Williamson County, Tennessee · SERC

DC Readiness
75.9
Excellent / 100

Greenfield (PIN HOOK - DAVIDSON) is a greenfield datacenter candidate site in Williamson County, Tennessee, interconnecting through SERC. It screens at 75.9/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 3.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationPIN HOOK
Substation voltage500 kV
Available capacity1,000 MW
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait3.7 yrs
Recent queue wait3.5 yrs
Completion rate15%
Withdrawal rate85%

Connectivity

Nearest IXPFlexential - Nashville/Brentwood (NAS01/04)
IXP distance4.0 mi
Fiber providers9
Fiber coverage78.9%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance342.7 mi

Site characteristics

Site typeGreenfield
Parcel ownerTENNESSEE VALLEY AUTHORITY
Land owner typeprivate
Buildability92.0/100
Land cover (NLCD)Developed, Low Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score62/100
Construction cost index116.8 (avg 100)

Location context

Nearest datacenterFlexential Nashville - Brentwood
DC distance4.0 mi
Nearest rail3.9 mi
Nearest gas pipeline1.8 mi
Nearest fiber route255.1 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.51¢/kWh
Industrial electricity6.34¢/kWh
Cooling degree days1,600
Heating degree days3,600
Land price / acre$7,148

Incentive detail: Sales tax exemption on DC equipment for $250M+ investments; no state income tax on wages.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
72
Speed to power15%
67
Fiber connectivity12%
91
Energy cost10%
90
Water risk8%
90
Natural hazard8%
62
Buildability7%
92
Labor market4%
50
DC cluster4%
80
Land / acreage3%
44
Construction cost3%
53
Gas pipeline2%
94
Tax incentive2%
100
Climate / cooling2%
45

Nearby comparable sites

Other scored datacenter candidate sites in Williamson County, ranked by DC Readiness.

Sites near Greenfield (PIN HOOK - DAVIDSON)
SiteTypeVoltageCapacityQueue waitScore
RUTHERFORDSubstation-Adjacent500 kV1,000 MW3.7 yrs76.5
Greenfield (RUTHERFORD - MAURY)Greenfield500 kV1,000 MW3.7 yrs74.3
EAST COOL SPRINGSSubstation-Adjacent161 kV100 MW3.7 yrs74.2
TAP153487Substation-Adjacent161 kV100 MW3.7 yrs74.1
TAP155166Substation-Adjacent161 kV100 MW3.7 yrs74.0
Greenfield (PIN HOOK - DAVIDSON)Greenfield500 kV1,000 MW3.7 yrs73.9
EAST FRANKLINSubstation-Adjacent161 kV100 MW3.7 yrs73.7
UNKNOWN115533Substation-Adjacent161 kV100 MW3.7 yrs72.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (PIN HOOK - DAVIDSON), Williamson County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.