TAP142382

Substation

South Carolina · GEORGIA POWER CO

Max voltage
115
kV

TAP142382 is an electric transmission substation in South Carolina, operated by GEORGIA POWER CO. It is classified as sub-transmission (115 kv) and connects 1 transmission line. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines1

Ownership & operation

OperatorGEORGIA POWER CO
Coordinates32.8826, -83.3171

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#31037115 kVGEORGIA POWER COIN SERVICE5.7 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP142382, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP142382 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
BONAIRESubstation-AdjacentGAHouston County500 kV1,000 MW5.8 yrs76.3
UNKNOWN114837Substation-AdjacentGABibb County230 kV300 MW5.8 yrs72.6
MID-GEORGIA COGENERATION FACILITYSubstation-AdjacentGAHouston County230 kV300 MW5.8 yrs70.7
Greenfield (UNKNOWN115783 - WARTHEN SUBSTA)GreenfieldGAJones County500 kV1,000 MW3.7 yrs70.6
UNKNOWN112146Substation-AdjacentGALaurens County230 kV300 MW3.7 yrs70.6
UNKNOWN113537Substation-AdjacentGATwiggs County230 kV300 MW3.7 yrs69.8
Greenfield (UNKNOWN115783 - WARTHEN SUBSTA)GreenfieldGAJones County500 kV1,000 MW3.7 yrs69.7
UNKNOWN113529Substation-AdjacentGAPutnam County230 kV300 MW3.7 yrs69.6

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP142382 substation, South Carolina. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.