WREN is an electric transmission substation in Oregon, operated by BONNEVILLE POWER ADMINISTRATION. It is classified as high-voltage (230 kv) and connects 5 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage230 kV
Min voltage115 kV
Voltage classHigh-voltage (230 kV)
Connected lines5

Ownership & operation

OperatorBONNEVILLE POWER ADMINISTRATION
Co-ownerCONSUMERS POWER, INC
StateOregon
Coordinates44.5907, -123.4286

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#67358230 kVBONNEVILLE POWER ADMINISTRATION41.8 mi
#67860230 kVBONNEVILLE POWER ADMINISTRATION25.7 mi
#67861115 kVCONSUMERS POWER, INC16.4 mi
#67862115 kVCONSUMERS POWER, INC9.4 mi
#77088115 kVCONSUMERS POWER, INC0.1 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of WREN, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near WREN substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
FRYSubstation-AdjacentORBenton County230 kV300 MW1.7 yrs72.8
WRENSubstation-AdjacentORBenton County230 kV300 MW1.7 yrs70.2
DIAMOND HILLSubstation-AdjacentORLane County230 kV300 MW1.7 yrs70.1
ALBANYSubstation-AdjacentORBenton County230 kV300 MW1.7 yrs69.6
TAP207025Substation-AdjacentORBenton County132 kV100 MW1.7 yrs68.5
SALEMSubstation-AdjacentORPolk County230 kV300 MW1.7 yrs68.2
MARYS RVIERSubstation-AdjacentORBenton County115 kV100 MW1.7 yrs68.1
UNKNOWN208741Substation-AdjacentORBenton County115 kV100 MW1.7 yrs67.7

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for WREN substation, Oregon. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.