TAP154467

Substation

Ohio · OHIO POWER CO

Max voltage
138
kV

TAP154467 is an electric transmission substation in Ohio, operated by OHIO POWER CO. It is classified as sub-transmission (138 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage138 kV
Min voltage138 kV
Voltage classSub-transmission (138 kV)
Connected lines3

Ownership & operation

OperatorOHIO POWER CO
StateOhio
Coordinates39.7097, -82.2933

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#14649138 kVOHIO POWER COIN SERVICE0.0 mi
#25311138 kVOHIO POWER COIN SERVICE18.7 mi
#46704138 kVOHIO POWER COIN SERVICE11.3 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP154467, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP154467 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
TAP141206Substation-AdjacentOHFairfield County345 kV600 MW3.2 yrs73.4
Greenfield (TAP141206 - WEST MILLERSPORT)GreenfieldOHLicking County345 kV600 MW3.2 yrs70.0
MILLERSPORTSubstation-AdjacentOHFairfield County138 kV100 MW3.2 yrs69.7
UNKNOWN154527Substation-AdjacentOHFairfield County138 kV100 MW3.2 yrs69.6
HARRISONSubstation-AdjacentOHFairfield County500 kV1,000 MW3.2 yrs69.5
WEST MILLERSPORTSubstation-AdjacentOHPerry County345 kV600 MW3.2 yrs69.4
Greenfield (FLATLICK - MARYSVILLE)GreenfieldOHVinton County765 kV1,000 MW3.2 yrs69.3
SOUTH BALTIMORESubstation-AdjacentOHFairfield County138 kV100 MW3.2 yrs68.9

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen