TAP135797

Substation

New York · NIAGARA MOHAWK POWER CORP.

Max voltage
115
kV

TAP135797 is an electric transmission substation in New York, operated by NIAGARA MOHAWK POWER CORP.. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

OperatorNIAGARA MOHAWK POWER CORP.
Coordinates43.1291, -73.8450

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#8558115 kVNIAGARA MOHAWK POWER CORP.IN SERVICE1.3 mi
#10616115 kVNIAGARA MOHAWK POWER CORP.IN SERVICE14.0 mi
#41079115 kVNIAGARA MOHAWK POWER CORP.IN SERVICE2.7 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP135797, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP135797 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
ROTTERDAMSubstation-AdjacentNYSchenectady County230 kV300 MW3.5 yrs67.2
FRONT STREETSubstation-AdjacentNYSchenectady County115 kV100 MW3.5 yrs65.6
EASTOVERSubstation-AdjacentNYRensselaer County230 kV300 MW3.5 yrs65.2
CURRY ROADSubstation-AdjacentNYSchenectady County115 kV100 MW3.5 yrs65.0
Troy Landfill Solar 2BrownfieldNYRensselaer3 MW64.9
TAP135866Substation-AdjacentNYSchenectady County115 kV100 MW3.5 yrs64.9
GENERAL ELECTRICSubstation-AdjacentNYSchenectady County115 kV100 MW3.5 yrs64.8
MAPLEWOODSubstation-AdjacentNYRensselaer County115 kV100 MW3.5 yrs64.6

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP135797 substation, New York. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.