JOHN STREET 1, 3, 4 & 5
SubstationNew York · CONNECTICUT LIGHT & POWER CO
JOHN STREET 1, 3, 4 & 5 is an electric transmission substation in New York, operated by CONNECTICUT LIGHT & POWER CO. It is classified as sub-transmission (115 kv) and connects 4 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #1283 | 115 kV | — | — | 0.1 mi |
| #10816 | 115 kV | CONNECTICUT LIGHT & POWER CO | IN SERVICE | 14.5 mi |
| #41583 | 115 kV | — | IN SERVICE | 0.7 mi |
| #47577 | 115 kV | — | — | 0.1 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of JOHN STREET 1, 3, 4 & 5, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| NO. WALL | Substation-Adjacent | CT | South Central Connecticut Planning Region | 345 kV | 600 MW | 3.5 yrs | 70.0 |
| FROST BRIDGE | Substation-Adjacent | CT | Naugatuck Valley Planning Region | 345 kV | 600 MW | 3.5 yrs | 70.0 |
| BRIDGEPORT RESCO | Substation-Adjacent | CT | Greater Bridgeport Planning Region | 345 kV | 600 MW | 3.5 yrs | 69.7 |
| UNKNOWN133278 | Substation-Adjacent | CT | South Central Connecticut Planning Region | 345 kV | 600 MW | 3.5 yrs | 69.4 |
| MANCHESTER | Substation-Adjacent | CT | Capitol Planning Region | 345 kV | 600 MW | 3.5 yrs | 69.1 |
| TAP136499 | Substation-Adjacent | CT | Capitol Planning Region | 345 kV | 600 MW | 3.5 yrs | 67.6 |
| BRIDGEPORT HARBOR | Substation-Adjacent | CT | Greater Bridgeport Planning Region | 345 kV | 600 MW | 3.5 yrs | 66.8 |
| FREIGHT | Substation-Adjacent | CT | Naugatuck Valley Planning Region | 115 kV | 100 MW | 3.5 yrs | 65.7 |
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for JOHN STREET 1, 3, 4 & 5 substation, New York. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.