COOLIDGE

Substation

New York · GREEN MOUNTAIN POWER CORP

Max voltage
345
kV

COOLIDGE is an electric transmission substation in New York, operated by GREEN MOUNTAIN POWER CORP. It is classified as high-voltage (345 kv) and connects 5 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage345 kV
Min voltage115 kV
Voltage classHigh-voltage (345 kV)
Connected lines5

Ownership & operation

OperatorGREEN MOUNTAIN POWER CORP
Co-ownerVERMONT ELECTRIC POWER CO
Coordinates43.3341, -72.6610

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#7524345 kVVERMONT ELECTRIC POWER COIN SERVICE27.4 mi
#28265345 kVVERMONT ELECTRIC POWER COIN SERVICE35.5 mi
#35039345 kVVERMONT ELECTRIC POWER COIN SERVICE51.0 mi
#7167115 kVVERMONT ELECTRIC POWER COIN SERVICE18.2 mi
#27693115 kVGREEN MOUNTAIN POWER CORPIN SERVICE14.0 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of COOLIDGE, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near COOLIDGE substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
WEST RUTLANDSubstation-AdjacentVTRutland County345 kV600 MW3.5 yrs70.6
NORTH RUTLANDSubstation-AdjacentVTRutland County115 kV100 MW3.5 yrs66.4
COOLIDGESubstation-AdjacentVTWindsor County345 kV600 MW3.5 yrs65.6
OZ RutlandGreenfieldVTRutland3.5 yrs64.8
Rutland Landfill (Stafford Hill)BrownfieldVTRutland2 MW64.6
Greenfield (WEST RUTLAND - COOLIDGE)GreenfieldVTWindsor County345 kV600 MW3.5 yrs64.4
Greenfield (WEST RUTLAND - COOLIDGE)GreenfieldVTRutland County345 kV600 MW3.5 yrs64.4
Greenfield (WEST RUTLAND - COOLIDGE)GreenfieldVTRutland County345 kV600 MW3.5 yrs64.2

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.