CARD`

Substation

New York · CONNECTICUT LIGHT & POWER CO

Max voltage
345
kV

CARD` is an electric transmission substation in New York, operated by CONNECTICUT LIGHT & POWER CO. It is classified as high-voltage (345 kv) and connects 7 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage345 kV
Min voltage115 kV
Voltage classHigh-voltage (345 kV)
Connected lines7

Ownership & operation

OperatorCONNECTICUT LIGHT & POWER CO
Coordinates41.6988, -72.2259

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#10713345 kVIN SERVICE28.8 mi
#7445345 kVCONNECTICUT LIGHT & POWER COIN SERVICE20.0 mi
#39227345 kVCONNECTICUT LIGHT & POWER COIN SERVICE29.3 mi
#25102115 kVCONNECTICUT LIGHT & POWER COIN SERVICE6.4 mi
#10715115 kVIN SERVICE10.7 mi
#10712115 kVIN SERVICE12.6 mi
#12040115 kVCONNECTICUT LIGHT & POWER COIN SERVICE9.5 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of CARD`, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near CARD` substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
MILLSTONESubstation-AdjacentCTSoutheastern Connecticut Planning Region345 kV600 MW3.5 yrs68.8
LAKE ROADSubstation-AdjacentCTNortheastern Connecticut Planning Region345 kV600 MW3.5 yrs68.2
TAP136499Substation-AdjacentCTCapitol Planning Region345 kV600 MW3.5 yrs67.6
CHASE HILLSubstation-AdjacentRIWashington County115 kV100 MW3.5 yrs67.1
EAST HARTFORDSubstation-AdjacentCTCapitol Planning Region115 kV100 MW3.5 yrs65.7
CARD`Substation-AdjacentCTSoutheastern Connecticut Planning Region345 kV600 MW3.5 yrs65.3
BARBOUR HILLSubstation-AdjacentCTCapitol Planning Region345 kV600 MW3.5 yrs65.2
MONTVILLESubstation-AdjacentCTSoutheastern Connecticut Planning Region345 kV600 MW3.5 yrs64.9

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for CARD` substation, New York. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.