WASCO

Substation

Nevada · PACIFIC GAS & ELECTRIC COMPANY

Max voltage
115
kV

WASCO is an electric transmission substation in Nevada, operated by PACIFIC GAS & ELECTRIC COMPANY. It is classified as sub-transmission (115 kv) and connects 2 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines2

Ownership & operation

OperatorPACIFIC GAS & ELECTRIC COMPANY
StateNevada
Coordinates35.6019, -119.3262

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#88628115 kVPACIFIC GAS & ELECTRIC COMPANYIN SERVICE2.8 mi
#92443115 kVPACIFIC GAS & ELECTRIC COMPANYIN SERVICE6.3 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of WASCO, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near WASCO substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
MIDWAYSubstation-AdjacentCAKern County500 kV1,000 MW5.8 yrs62.5
SYCAMORE COGENSubstation-AdjacentCAKern County230 kV300 MW5.8 yrs60.8
OMARSubstation-AdjacentCAKern County230 kV300 MW5.8 yrs60.0
KERNSubstation-AdjacentCAKern County230 kV300 MW5.8 yrs60.0
SUNSETSubstation-AdjacentCASan Luis Obispo County230 kV300 MW5.8 yrs59.0
Greenfield (VINCENT - MIDWAY)GreenfieldCAKern County500 kV1,000 MW5.8 yrs58.3
Greenfield (VINCENT - MIDWAY)GreenfieldCAKern County500 kV1,000 MW5.8 yrs58.3
BAKERSFIELDSubstation-AdjacentCAKern County230 kV300 MW5.8 yrs58.2

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for WASCO substation, Nevada. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.