DWORSHAK

Substation

Montana · BONNEVILLE POWER ADMINISTRATION

Max voltage
500
kV

DWORSHAK is an electric transmission substation in Montana, operated by BONNEVILLE POWER ADMINISTRATION. It is classified as extra-high-voltage (500 kv) and connects 1 transmission line. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage500 kV
Min voltage500 kV
Voltage classExtra-high-voltage (500 kV)
Connected lines1

Ownership & operation

OperatorBONNEVILLE POWER ADMINISTRATION
StateMontana
Coordinates46.5284, -116.3672

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#67235500 kVBONNEVILLE POWER ADMINISTRATIONIN SERVICE90.3 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of DWORSHAK, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near DWORSHAK substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
DWORSHAKSubstation-AdjacentIDLewis County500 kV1,000 MW1.1 yrs72.8
DWORSHAKSubstation-AdjacentIDLewis County500 kV1,000 MW2.0 yrs72.2
Greenfield (DWORSHAK - TAFT)GreenfieldIDLatah County500 kV1,000 MW1.1 yrs70.0
Greenfield (DWORSHAK - TAFT)GreenfieldIDLatah County500 kV1,000 MW1.1 yrs70.0
Greenfield (DWORSHAK - TAFT)GreenfieldIDLatah County500 kV1,000 MW1.1 yrs68.7
Greenfield (HATWAI - DWORSHAK)GreenfieldIDNez Perce County500 kV1,000 MW2.0 yrs68.0
Greenfield (DWORSHAK - TAFT)GreenfieldIDLatah County500 kV1,000 MW1.1 yrs67.7
Greenfield (DWORSHAK - TAFT)GreenfieldIDLatah County500 kV1,000 MW1.1 yrs67.6

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen