WEST NEW MADRID

Substation

Missouri · UNION ELECTRIC CO - (MO)

Max voltage
500
kV

WEST NEW MADRID is an electric transmission substation in Missouri, operated by UNION ELECTRIC CO - (MO). It is classified as extra-high-voltage (500 kv) and connects 6 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage500 kV
Min voltage345 kV
Voltage classExtra-high-voltage (500 kV)
Connected lines6

Ownership & operation

OperatorUNION ELECTRIC CO - (MO)
Coordinates36.4086, -89.7467

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#22046500 kVIN SERVICE54.6 mi
#45041500 kVUNION ELECTRIC CO - (MO)IN SERVICE1.0 mi
#2182345 kVUNION ELECTRIC CO - (MO)IN SERVICE33.2 mi
#5443345 kVUNION ELECTRIC CO - (MO)IN SERVICE1.0 mi
#32477345 kVUNION ELECTRIC CO - (MO)IN SERVICE1.0 mi
#48999345 kVUNION ELECTRIC CO - (MO)IN SERVICE30.4 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of WEST NEW MADRID, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near WEST NEW MADRID substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
DELLSubstation-AdjacentMONew Madrid County500 kV1,000 MW1.4 yrs72.9
NEW MADRIDSubstation-AdjacentMONew Madrid County500 kV1,000 MW1.4 yrs71.1
WEST NEW MADRIDSubstation-AdjacentMONew Madrid County500 kV1,000 MW1.4 yrs70.1
TAP154742Substation-AdjacentMONew Madrid County345 kV600 MW1.4 yrs68.4
Greenfield (WEST NEW MADRID - DELL)GreenfieldMODunklin County500 kV1,000 MW1.4 yrs65.8
Greenfield (WEST NEW MADRID - DELL)GreenfieldTNLake County500 kV1,000 MW1.4 yrs65.7
Greenfield (WEST NEW MADRID - DELL)GreenfieldMODunklin County500 kV1,000 MW1.4 yrs64.7
Greenfield (WEST NEW MADRID - DELL)GreenfieldMOPemiscot County500 kV1,000 MW1.4 yrs64.7

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for WEST NEW MADRID substation, Missouri. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.