TIPTONVILLE
SubstationMissouri · TENNESSEE VALLEY AUTHORITY
TIPTONVILLE is an electric transmission substation in Missouri, operated by TENNESSEE VALLEY AUTHORITY. It is classified as sub-transmission (138 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Ownership & operation
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #3218 | 161 kV | UNION ELECTRIC CO - (MO) | IN SERVICE | 16.0 mi |
| #14415 | 161 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 20.4 mi |
| #27033 | 161 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 7.8 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of TIPTONVILLE, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| DELL | Substation-Adjacent | MO | New Madrid County | 500 kV | 1,000 MW | 1.4 yrs | 72.9 |
| NEW MADRID | Substation-Adjacent | MO | New Madrid County | 500 kV | 1,000 MW | 1.4 yrs | 71.1 |
| MOSCOW SOUTH WEST STATION | Substation-Adjacent | KY | Hickman County | 161 kV | 100 MW | 3.7 yrs | 70.9 |
| WEST NEW MADRID | Substation-Adjacent | MO | New Madrid County | 500 kV | 1,000 MW | 1.4 yrs | 70.1 |
| UNION CITY | Substation-Adjacent | TN | Obion County | 161 kV | 100 MW | 3.7 yrs | 70.1 |
| TAP160398 | Substation-Adjacent | TN | Obion County | 161 kV | 100 MW | 3.7 yrs | 68.9 |
| NORTH UNION CITY | Substation-Adjacent | TN | Obion County | 161 kV | 100 MW | 3.7 yrs | 68.5 |
| TAP154683 | Substation-Adjacent | TN | Obion County | 161 kV | 100 MW | 3.7 yrs | 68.4 |
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for TIPTONVILLE substation, Missouri. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.