TAP153677

Substation

Missouri · EMPIRE DISTRICT ELECTRIC CO

Max voltage
161
kV

TAP153677 is an electric transmission substation in Missouri, operated by EMPIRE DISTRICT ELECTRIC CO. It is classified as sub-transmission (138 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage161 kV
Min voltage161 kV
Voltage classSub-transmission (138 kV)
Connected lines3

Ownership & operation

OperatorEMPIRE DISTRICT ELECTRIC CO
Coordinates37.6692, -93.4862

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#18719161 kVEMPIRE DISTRICT ELECTRIC COIN SERVICE12.8 mi
#28160161 kVEMPIRE DISTRICT ELECTRIC COIN SERVICE0.1 mi
#43406161 kVIN SERVICE15.3 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP153677, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP153677 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
MORGANSubstation-AdjacentMODade County345 kV600 MW1.4 yrs70.2
Greenfield (MORGAN - BROOKLINE)GreenfieldMOGreene County345 kV600 MW1.4 yrs68.8
TAP153678Substation-AdjacentMOGreene County161 kV100 MW1.4 yrs68.3
UNKNOWN117607Substation-AdjacentMOGreene County161 kV100 MW1.4 yrs68.2
Greenfield (MORGAN - BROOKLINE)GreenfieldMOGreene County345 kV600 MW1.4 yrs67.5
UNKNOWN117663Substation-AdjacentMOGreene County161 kV100 MW1.4 yrs66.6
UNKNOWN121634Substation-AdjacentMOCedar County161 kV100 MW1.4 yrs66.4
UNKNOWN117452Substation-AdjacentMODade County161 kV100 MW1.4 yrs65.3

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.