TAP170793

Substation

Minnesota

Max voltage
115
kV

TAP170793 is an electric transmission substation in Minnesota. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

Operator not catalogued for this substation.

Coordinates45.8912, -95.3699

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#59829115 kVIN SERVICE1.1 mi
#59830115 kVIN SERVICE10.1 mi
#59831115 kVIN SERVICE1.1 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP170793, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP170793 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
Greenfield (COAL CREEK - DICKINSON)GreenfieldMNPope County400 kV600 MW1.4 yrs70.2
Greenfield (COAL CREEK - DICKINSON)GreenfieldMNPope County400 kV600 MW1.4 yrs70.2
Greenfield (COAL CREEK - DICKINSON)GreenfieldMNPope County400 kV600 MW1.4 yrs69.9
Greenfield (COAL CREEK - DICKINSON)GreenfieldMNStevens County400 kV600 MW1.4 yrs68.0
Greenfield (QUARRY - ALEXANDRIA)GreenfieldMNTodd County345 kV600 MW1.4 yrs67.0
MRES ALEXANDRIASubstation-AdjacentMNDouglas County115 kV100 MW1.4 yrs67.0
Greenfield (COAL CREEK - DICKINSON)GreenfieldMNStearns County400 kV600 MW1.4 yrs66.9
ALEXANDRIASubstation-AdjacentMNDouglas County345 kV600 MW1.4 yrs66.9

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP170793 substation, Minnesota. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.