TAP135059

Substation

Minnesota

Max voltage
115
kV

TAP135059 is an electric transmission substation in Minnesota. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

Operator not catalogued for this substation.

Coordinates45.9208, -95.5291

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#14449115 kVIN SERVICE6.1 mi
#25823115 kVIN SERVICE7.2 mi
#47765115 kVIN SERVICE0.4 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP135059, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP135059 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
Greenfield (COAL CREEK - DICKINSON)GreenfieldMNPope County400 kV600 MW1.4 yrs70.2
Greenfield (COAL CREEK - DICKINSON)GreenfieldMNPope County400 kV600 MW1.4 yrs70.2
Greenfield (COAL CREEK - DICKINSON)GreenfieldMNPope County400 kV600 MW1.4 yrs69.9
Greenfield (ALEXANDRIA - BISON)GreenfieldMNGrant County345 kV600 MW1.4 yrs69.3
Greenfield (ALEXANDRIA - BISON)GreenfieldMNGrant County345 kV600 MW1.4 yrs68.9
Greenfield (COAL CREEK - DICKINSON)GreenfieldMNGrant County400 kV600 MW1.4 yrs68.7
UNKNOWN130171Substation-AdjacentMNStevens County115 kV100 MW1.4 yrs68.1
Greenfield (COAL CREEK - DICKINSON)GreenfieldMNStevens County400 kV600 MW1.4 yrs68.0

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen