TAP144567

Substation

Michigan · CONSUMERS ENERGY CO

Max voltage
138
kV

TAP144567 is an electric transmission substation in Michigan, operated by CONSUMERS ENERGY CO. It is classified as sub-transmission (138 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage138 kV
Min voltage138 kV
Voltage classSub-transmission (138 kV)
Connected lines3

Ownership & operation

OperatorCONSUMERS ENERGY CO
Coordinates44.6026, -83.4681

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#1728138 kVCONSUMERS ENERGY COIN SERVICE6.1 mi
#7438138 kVCONSUMERS ENERGY COIN SERVICE1.3 mi
#41688138 kVCONSUMERS ENERGY COIN SERVICE18.0 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP144567, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP144567 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
WHITTEMORESubstation-AdjacentMIArenac County138 kV100 MW2.2 yrs64.4
TAP144567Substation-AdjacentMIAlcona County138 kV100 MW2.2 yrs63.8
VIKING ENERGY OF LINCOLNSubstation-AdjacentMIAlcona County138 kV100 MW2.2 yrs62.1
UNKNOWN144068Substation-AdjacentMIAlpena County138 kV100 MW2.2 yrs61.2
Greenfield (UNKNOWN128888 - EAST TAWAS)GreenfieldMIIosco County138 kV100 MW2.2 yrs60.8
UNKNOWN128888Substation-AdjacentMIAlcona County138 kV100 MW2.2 yrs60.7
Greenfield (UNKNOWN128836 - EAST TAWAS)GreenfieldMIArenac County138 kV100 MW2.2 yrs60.2
Greenfield (FOUR MILE HYDROPOWER PROJECT -)GreenfieldMIAlpena County138 kV100 MW2.2 yrs60.1

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen