TAP139932

Substation

Michigan · INDIANA MICHIGAN POWER CO

Max voltage
138
kV

TAP139932 is an electric transmission substation in Michigan, operated by INDIANA MICHIGAN POWER CO. It is classified as sub-transmission (138 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage138 kV
Min voltage138 kV
Voltage classSub-transmission (138 kV)
Connected lines3

Ownership & operation

OperatorINDIANA MICHIGAN POWER CO
Coordinates41.7222, -86.5071

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#2092138 kVINDIANA MICHIGAN POWER COIN SERVICE2.0 mi
#18718138 kVINDIANA MICHIGAN POWER COIN SERVICE0.2 mi
#20886138 kVINDIANA MICHIGAN POWER COIN SERVICE2.0 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP139932, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP139932 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
DUMONTSubstation-AdjacentINSt. Joseph County765 kV1,000 MW2.2 yrs80.4
ST. JOHNSubstation-AdjacentINSt. Joseph County345 kV600 MW2.2 yrs80.3
KENZIE CREEKSubstation-AdjacentMICass County345 kV600 MW2.2 yrs77.2
COOKSubstation-AdjacentMIBerrien County765 kV1,000 MW2.2 yrs75.5
JACKSON ROADSubstation-AdjacentINSt. Joseph County345 kV600 MW3.0 yrs73.7
OLIVESubstation-AdjacentINLaPorte County345 kV600 MW2.2 yrs73.5
Greenfield (KENZIE CREEK - COOK)GreenfieldMICass County345 kV600 MW2.2 yrs73.4
DUMONTSubstation-AdjacentINMarshall County765 kV1,000 MW3.0 yrs72.7

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen