TAP138708

Substation

Michigan · THUMB ELECTRIC COOP OF MICH

Max voltage
120
kV

TAP138708 is an electric transmission substation in Michigan, operated by THUMB ELECTRIC COOP OF MICH. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage120 kV
Min voltage120 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

OperatorTHUMB ELECTRIC COOP OF MICH
Coordinates43.2625, -83.3800

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#11926120 kVTHUMB ELECTRIC COOP OF MICHIN SERVICE14.6 mi
#13041120 kVIN SERVICE20.7 mi
#22610120 kVTHUMB ELECTRIC COOP OF MICHIN SERVICE0.0 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP138708, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP138708 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN128533Substation-AdjacentMIGenesee County345 kV600 MW2.2 yrs75.1
BAUERSubstation-AdjacentMITuscola County345 kV600 MW2.2 yrs72.1
THETFORDSubstation-AdjacentMIGenesee County345 kV600 MW2.2 yrs71.3
TAP144602Substation-AdjacentMITuscola County345 kV600 MW2.2 yrs70.8
UNKNOWN128636Substation-AdjacentMIGenesee County138 kV100 MW2.2 yrs69.6
HAMPTONSubstation-AdjacentMIBay County345 kV600 MW2.2 yrs69.3
UNKNOWN161569Substation-AdjacentMIGenesee County138 kV100 MW2.2 yrs68.8
TAP138700Substation-AdjacentMIGenesee County138 kV100 MW2.2 yrs68.6

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen