GAYLORD - CONSUMERS

Substation

Michigan · WOLVERINE POWER SUPPLY COOP

Max voltage
138
kV

GAYLORD - CONSUMERS is an electric transmission substation in Michigan, operated by WOLVERINE POWER SUPPLY COOP. It is classified as sub-transmission (138 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage138 kV
Min voltage138 kV
Voltage classSub-transmission (138 kV)
Connected lines3

Ownership & operation

OperatorWOLVERINE POWER SUPPLY COOP
Coordinates45.0301, -84.7031

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#28661138 kVIN SERVICE1.3 mi
#35857138 kVIN SERVICE1.6 mi
#41113138 kVWOLVERINE POWER SUPPLY COOP0.1 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of GAYLORD - CONSUMERS, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near GAYLORD - CONSUMERS substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
LIVINGSTONSubstation-AdjacentMIOtsego County345 kV600 MW2.2 yrs73.3
LIVINGSTON GENERATING STATIONSubstation-AdjacentMIOtsego County138 kV100 MW2.2 yrs68.5
GAYLORD - CONSUMERSSubstation-AdjacentMIOtsego County138 kV100 MW2.2 yrs68.0
UNKNOWN133923Substation-AdjacentMIOtsego County138 kV100 MW2.2 yrs67.7
UNKNOWN128860Substation-AdjacentMIOtsego County138 kV100 MW2.2 yrs67.4
Greenfield (LIVINGSTON - KEYSTONE)GreenfieldMIAntrim County345 kV600 MW2.2 yrs67.2
GAYLORD - WOLVERINESubstation-AdjacentMIOtsego County138 kV100 MW2.2 yrs67.1
Greenfield (LIVINGSTON - GALLAGHER)GreenfieldMIOtsego County345 kV600 MW2.2 yrs67.0

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for GAYLORD - CONSUMERS substation, Michigan. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.