BYRON

Substation

Michigan · COMMONWEALTH EDISON CO

Max voltage
345
kV

BYRON is an electric transmission substation in Michigan, operated by COMMONWEALTH EDISON CO. It is classified as high-voltage (345 kv) and connects 6 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage345 kV
Min voltage345 kV
Voltage classHigh-voltage (345 kV)
Connected lines6

Ownership & operation

OperatorCOMMONWEALTH EDISON CO
Coordinates42.0740, -89.2867

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#1688345 kVCOMMONWEALTH EDISON COIN SERVICE21.7 mi
#20645345 kVCOMMONWEALTH EDISON COIN SERVICE21.6 mi
#37380345 kVCOMMONWEALTH EDISON COIN SERVICE13.7 mi
#38852345 kV0.2 mi
#42898345 kVCOMMONWEALTH EDISON COIN SERVICE13.7 mi
#43933345 kVIN SERVICE19.6 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of BYRON, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near BYRON substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
BYRONSubstation-AdjacentILOgle County345 kV600 MW2.2 yrs75.2
CHERRY VALLEYSubstation-AdjacentILBoone County345 kV600 MW2.2 yrs74.9
TAP137908Substation-AdjacentILBoone County345 kV600 MW2.2 yrs73.4
UNKNOWN122197Substation-AdjacentILLee County345 kV600 MW2.2 yrs72.6
NELSONSubstation-AdjacentILLee County345 kV600 MW2.2 yrs72.4
EASY ROADSubstation-AdjacentILLee County345 kV600 MW2.2 yrs72.2
TAP137909Substation-AdjacentILWinnebago County345 kV600 MW2.2 yrs71.9
WEMPLETOWNSubstation-AdjacentILWinnebago County345 kV600 MW2.2 yrs71.7

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for BYRON substation, Michigan. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.