CUMBERLAND 500KV

Substation

Illinois

Max voltage
500
kV

CUMBERLAND 500KV is an electric transmission substation in Illinois. It is classified as extra-high-voltage (500 kv) and connects 1 transmission line. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage500 kV
Min voltage500 kV
Voltage classExtra-high-voltage (500 kV)
Connected lines1

Ownership & operation

Operator not catalogued for this substation.

Coordinates37.0246, -88.3938

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#21734500 kVIN SERVICE77.6 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of CUMBERLAND 500KV, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near CUMBERLAND 500KV substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
SHAWNEESubstation-AdjacentILMassac County500 kV1,000 MW4.6 yrs81.3
CUMBERLAND 500KVSubstation-AdjacentKYMarshall County500 kV1,000 MW4.6 yrs76.5
UNKNOWN121869Substation-AdjacentILMassac County161 kV100 MW4.6 yrs70.4
UNKNOWN155637Substation-AdjacentKYMcCracken County161 kV100 MW4.6 yrs70.2
UNKNOWN122861Substation-AdjacentKYMcCracken County161 kV100 MW4.6 yrs69.7
UNKNOWN155633Substation-AdjacentKYMarshall County161 kV100 MW4.6 yrs69.2
TAP153781Substation-AdjacentKYMcCracken County161 kV100 MW4.6 yrs67.8
DOVERSubstation-AdjacentKYLyon County161 kV100 MW4.6 yrs67.6

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for CUMBERLAND 500KV substation, Illinois. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.