TAP204691

Substation

Idaho · CITY OF IDAHO FALLS - (ID)

Max voltage
161
kV

TAP204691 is an electric transmission substation in Idaho, operated by CITY OF IDAHO FALLS - (ID). It is classified as sub-transmission (138 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage161 kV
Min voltage161 kV
Voltage classSub-transmission (138 kV)
Connected lines3

Ownership & operation

OperatorCITY OF IDAHO FALLS - (ID)
Co-ownerPACIFICORP
StateIdaho
Coordinates43.4397, -112.1030

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#69576161 kVPACIFICORP2.1 mi
#69577161 kVPACIFICORP1.4 mi
#69578161 kVCITY OF IDAHO FALLS - (ID)1.8 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP204691, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP204691 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
RIGBYSubstation-AdjacentIDMadison County230 kV300 MW2.0 yrs71.8
GOSHENSubstation-AdjacentIDBingham County345 kV600 MW2.0 yrs69.7
AMMONSubstation-AdjacentIDBonneville County161 kV100 MW2.0 yrs69.5
TAP204670Substation-AdjacentIDBonneville County161 kV100 MW2.0 yrs68.6
WASHINGTONSubstation-AdjacentIDBonneville County161 kV100 MW2.0 yrs68.3
JOLLY HILLSubstation-AdjacentIDBonneville County161 kV100 MW2.0 yrs67.5
TAP204706Substation-AdjacentIDMadison County161 kV100 MW2.0 yrs66.8
TAP204750Substation-AdjacentIDBingham County138 kV100 MW2.0 yrs66.6

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP204691 substation, Idaho. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.