ELY

Substation

Florida · FLORIDA POWER & LIGHT CO

Max voltage
138
kV

ELY is an electric transmission substation in Florida, operated by FLORIDA POWER & LIGHT CO. It is classified as sub-transmission (138 kv) and connects 2 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage138 kV
Min voltage138 kV
Voltage classSub-transmission (138 kV)
Connected lines2

Ownership & operation

OperatorFLORIDA POWER & LIGHT CO
StateFlorida
Coordinates26.2456, -80.1431

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#2810138 kVFLORIDA POWER & LIGHT COIN SERVICE5.0 mi
#33749138 kVFLORIDA POWER & LIGHT COIN SERVICE2.0 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of ELY, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near ELY substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
OAKLAND PARKSubstation-AdjacentFLBroward County230 kV300 MW3.6 yrs76.8
YAMATOSubstation-AdjacentFLPalm Beach County230 kV300 MW3.6 yrs76.7
DEERFIELD BEACHSubstation-AdjacentFLBroward County230 kV300 MW3.6 yrs76.3
WOODLANDSSubstation-AdjacentFLBroward County230 kV300 MW3.6 yrs75.9
GERMANTOWNSubstation-AdjacentFLPalm Beach County230 kV300 MW3.6 yrs75.8
UNKNOWN108642Substation-AdjacentFLBroward County230 kV300 MW3.6 yrs75.8
DELMARSubstation-AdjacentFLBroward County230 kV300 MW3.6 yrs75.8
BUTTSSubstation-AdjacentFLBroward County230 kV300 MW3.6 yrs75.6

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for ELY substation, Florida. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.