TAP205886

Substation

Colorado · HIGHLINE ELECTRIC ASSN

Max voltage
115
kV

TAP205886 is an electric transmission substation in Colorado, operated by HIGHLINE ELECTRIC ASSN. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

OperatorHIGHLINE ELECTRIC ASSN
Co-ownerTRI-STATE G & T ASSN, INC
Coordinates40.4461, -102.0512

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#71872115 kVTRI-STATE G & T ASSN, INC5.9 mi
#71873115 kVHIGHLINE ELECTRIC ASSN9.2 mi
#74576115 kVHIGHLINE ELECTRIC ASSN9.4 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP205886, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP205886 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
WRAYSubstation-AdjacentCOYuma County230 kV300 MW1.7 yrs67.1
UNKNOWN206843Substation-AdjacentNEChase County115 kV100 MW3.5 yrs65.0
UNKNOWN205889Substation-AdjacentCOPhillips County115 kV100 MW1.7 yrs62.8
UNKNOWN131764Substation-AdjacentNEPerkins County115 kV100 MW3.5 yrs62.6
UNKNOWN131952Substation-AdjacentNEChase County115 kV100 MW3.5 yrs61.8
UNKNOWN205863Substation-AdjacentCOYuma County115 kV100 MW1.7 yrs61.2
UNKNOWN205887Substation-AdjacentNEChase County115 kV100 MW1.7 yrs61.1
UNKNOWN206843Substation-AdjacentNEChase County115 kV100 MW1.7 yrs60.9

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.