TAP205869

Substation

Colorado · HIGHLINE ELECTRIC ASSN

Max voltage
115
kV

TAP205869 is an electric transmission substation in Colorado, operated by HIGHLINE ELECTRIC ASSN. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

OperatorHIGHLINE ELECTRIC ASSN
Coordinates40.6646, -103.1320

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#71853115 kVHIGHLINE ELECTRIC ASSN0.0 mi
#71854115 kVHIGHLINE ELECTRIC ASSN4.0 mi
#71862115 kVHIGHLINE ELECTRIC ASSN5.2 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP205869, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP205869 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
SPRING CANYONSubstation-AdjacentCOLogan County230 kV300 MW1.7 yrs65.6
PEETZ TABLE WIND ENERGYSubstation-AdjacentCOLogan County230 kV300 MW1.7 yrs63.9
UNKNOWN201534Substation-AdjacentCOLogan County230 kV300 MW1.7 yrs63.2
UNKNOWN205850Substation-AdjacentCOMorgan County115 kV100 MW1.7 yrs63.2
UNKNOWN205871Substation-AdjacentCOLogan County115 kV100 MW1.7 yrs62.2
STERLINGSubstation-AdjacentCOLogan County138 kV100 MW1.7 yrs61.6
UNKNOWN201554Substation-AdjacentNECheyenne County115 kV100 MW1.7 yrs60.7
PEETZSubstation-AdjacentCOLogan County115 kV100 MW1.7 yrs60.6

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.