TAP205667

Substation

Colorado · SOUTHEAST COLORADO POWER ASSN

Max voltage
230
kV

TAP205667 is an electric transmission substation in Colorado, operated by SOUTHEAST COLORADO POWER ASSN. It is classified as high-voltage (230 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage230 kV
Min voltage230 kV
Voltage classHigh-voltage (230 kV)
Connected lines3

Ownership & operation

OperatorSOUTHEAST COLORADO POWER ASSN
Co-ownerTRI-STATE G & T ASSN, INC
Coordinates37.7045, -102.6089

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#68867230 kVTRI-STATE G & T ASSN, INC43.9 mi
#72177230 kVSOUTHEAST COLORADO POWER ASSN0.0 mi
#72178230 kVSOUTHEAST COLORADO POWER ASSN0.1 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP205667, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP205667 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
COLORADO GREENSubstation-AdjacentCOProwers County230 kV300 MW1.7 yrs62.6
COLORADO GREEN HOLDINGS LLCSubstation-AdjacentCOProwers County230 kV300 MW1.7 yrs62.5
UNKNOWN201396Substation-AdjacentCOBent County230 kV300 MW1.7 yrs61.8
UNKNOWN208108Substation-AdjacentCOKiowa County115 kV100 MW1.7 yrs61.2
UNKNOWN208110Substation-AdjacentCOProwers County115 kV100 MW1.7 yrs58.8
TAP208106Substation-AdjacentCOProwers County115 kV100 MW1.7 yrs58.2
TAP208107Substation-AdjacentCOProwers County115 kV100 MW1.7 yrs58.1
TAP206905Substation-AdjacentCOProwers County115 kV100 MW1.7 yrs58.1

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.