ROCKPORT

Substation

Colorado · WAPA-- WESTERN AREA POWER ADMINISTRATION

Max voltage
115
kV

ROCKPORT is an electric transmission substation in Colorado, operated by WAPA-- WESTERN AREA POWER ADMINISTRATION. It is classified as sub-transmission (115 kv) and connects 2 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines2

Ownership & operation

OperatorWAPA-- WESTERN AREA POWER ADMINISTRATION
Coordinates40.8990, -104.8110

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#68914115 kVWAPA-- WESTERN AREA POWER ADMINISTRATION12.2 mi
#72281115 kVWAPA-- WESTERN AREA POWER ADMINISTRATION6.8 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of ROCKPORT, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near ROCKPORT substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN206586Substation-AdjacentWYLaramie County230 kV300 MW1.7 yrs76.0
UNKNOWN205186Substation-AdjacentWYLaramie County230 kV300 MW1.7 yrs72.2
UNKNOWN202330Substation-AdjacentWYLaramie County138 kV100 MW1.7 yrs71.6
UNKNOWN203998Substation-AdjacentWYLaramie County230 kV300 MW1.7 yrs71.2
UNKNOWN202329Substation-AdjacentWYLaramie County115 kV100 MW1.7 yrs70.8
UNKNOWN202336Substation-AdjacentWYLaramie County161 kV100 MW1.7 yrs70.2
UNKNOWN202331Substation-AdjacentWYLaramie County138 kV100 MW1.7 yrs69.9
UNKNOWN202328Substation-AdjacentWYLaramie County115 kV100 MW1.7 yrs69.6

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for ROCKPORT substation, Colorado. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.