PEETZ

Substation

Colorado · WAPA-- WESTERN AREA POWER ADMINISTRATION

Max voltage
115
kV

PEETZ is an electric transmission substation in Colorado, operated by WAPA-- WESTERN AREA POWER ADMINISTRATION. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

OperatorWAPA-- WESTERN AREA POWER ADMINISTRATION
Coordinates40.9499, -103.1137

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#68911115 kVWAPA-- WESTERN AREA POWER ADMINISTRATION22.9 mi
#68912115 kVWAPA-- WESTERN AREA POWER ADMINISTRATION16.4 mi
#72269115 kVWAPA-- WESTERN AREA POWER ADMINISTRATION2.3 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of PEETZ, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near PEETZ substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN202177Substation-AdjacentNECheyenne County345 kV600 MW1.7 yrs71.2
UNKNOWN202159Substation-AdjacentNECheyenne County230 kV300 MW1.7 yrs69.8
UNKNOWN202159Substation-AdjacentNECheyenne County230 kV300 MW3.5 yrs67.0
SPRING CANYONSubstation-AdjacentCOLogan County230 kV300 MW1.7 yrs65.6
Greenfield (UNKNOWN202179 - UNKNOWN202177)GreenfieldNECheyenne County345 kV600 MW3.5 yrs65.4
Greenfield (UNKNOWN202179 - UNKNOWN202177)GreenfieldNECheyenne County345 kV600 MW3.5 yrs64.9
Greenfield (LARAMIE RIVER - UNKNOWN202177)GreenfieldNECheyenne County345 kV600 MW1.7 yrs64.4
Sidney (NE)BrownfieldNECheyenne County230 kV3 MW3.5 yrs64.1

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for PEETZ substation, Colorado. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.