BONANZA

Substation

Colorado · MOON LAKE ELECTRIC ASSN INC

Max voltage
345
kV

BONANZA is an electric transmission substation in Colorado, operated by MOON LAKE ELECTRIC ASSN INC. It is classified as high-voltage (345 kv) and connects 2 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage345 kV
Min voltage138 kV
Voltage classHigh-voltage (345 kV)
Connected lines2

Ownership & operation

OperatorMOON LAKE ELECTRIC ASSN INC
Co-ownerTRI-STATE G & T ASSN, INC
Coordinates40.0859, -109.2905

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#67305345 kVTRI-STATE G & T ASSN, INC100.9 mi
#71967138 kVMOON LAKE ELECTRIC ASSN INC26.5 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of BONANZA, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near BONANZA substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
BONANZASubstation-AdjacentUTUintah County345 kV600 MW1.7 yrs67.5
VERNALSubstation-AdjacentUTUintah County138 kV100 MW1.7 yrs66.1
ANADARDKO-CHAPITASubstation-AdjacentUTUintah County138 kV100 MW1.7 yrs64.8
Greenfield (BONANZA - MONA)GreenfieldUTUintah County345 kV600 MW1.7 yrs64.6
TAP205948Substation-AdjacentUTUintah County138 kV100 MW1.7 yrs64.3
Greenfield (BONANZA - MONA)GreenfieldUTUintah County345 kV600 MW1.7 yrs63.0
TAP205934Substation-AdjacentUTUintah County138 kV100 MW1.7 yrs62.4
TAP208899Substation-AdjacentUTUintah County138 kV100 MW1.7 yrs62.0

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen