RAVENSWOOD

Substation

California · PACIFIC GAS & ELECTRIC COMPANY

Max voltage
230
kV

RAVENSWOOD is an electric transmission substation in California, operated by PACIFIC GAS & ELECTRIC COMPANY. It is classified as high-voltage (230 kv) and connects 11 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage230 kV
Min voltage115 kV
Voltage classHigh-voltage (230 kV)
Connected lines11

Ownership & operation

OperatorPACIFIC GAS & ELECTRIC COMPANY
Coordinates37.4930, -122.1379

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#88031230 kVIN SERVICE12.0 mi
#83860230 kVIN SERVICE9.0 mi
#89224230 kVIN SERVICE37.3 mi
#91135230 kVIN SERVICE12.0 mi
#81908115 kVPACIFIC GAS & ELECTRIC COMPANYIN SERVICE4.0 mi
#87813115 kVIN SERVICE7.2 mi
#88625115 kVIN SERVICE12.1 mi
#86852115 kVIN SERVICE7.3 mi
#82562115 kVPACIFIC GAS & ELECTRIC COMPANYIN SERVICE1.7 mi
#84565115 kVPACIFIC GAS & ELECTRIC COMPANYIN SERVICE1.7 mi
#85889115 kVIN SERVICE7.2 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of RAVENSWOOD, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near RAVENSWOOD substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
METCALF 1Substation-AdjacentCASanta Clara County500 kV1,000 MW5.7 yrs65.2
LOS ESTEROSSubstation-AdjacentCAAlameda County230 kV300 MW5.7 yrs64.1
MARTINSubstation-AdjacentCASan Mateo County230 kV300 MW5.7 yrs63.4
ROSSMOORSubstation-AdjacentCAContra Costa County230 kV300 MW5.7 yrs62.7
EMBARCADEROSubstation-AdjacentCAContra Costa County230 kV300 MW5.7 yrs62.4
CASTRO VALLEYSubstation-AdjacentCAAlameda County230 kV300 MW5.7 yrs62.4
VINEYARDSubstation-AdjacentCAAlameda County230 kV300 MW5.7 yrs62.2
POTREROSubstation-AdjacentCASan Mateo County230 kV300 MW5.7 yrs62.1

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for RAVENSWOOD substation, California. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.