MIRAGE
SubstationCalifornia · IMPERIAL IRRIGATION DISTRICT
MIRAGE is an electric transmission substation in California, operated by IMPERIAL IRRIGATION DISTRICT. It is classified as high-voltage (230 kv) and connects 9 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Ownership & operation
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #86920 | 230 kV | IMPERIAL IRRIGATION DISTRICT | IN SERVICE | 19.9 mi |
| #90392 | 230 kV | — | IN SERVICE | 6.2 mi |
| #91053 | 230 kV | IMPERIAL IRRIGATION DISTRICT | IN SERVICE | 46.6 mi |
| #91244 | 230 kV | IMPERIAL IRRIGATION DISTRICT | IN SERVICE | 0.1 mi |
| #86024 | 230 kV | — | IN SERVICE | 15.5 mi |
| #88076 | 115 kV | SOUTHERN CALIFORNIA EDISON | IN SERVICE | 6.5 mi |
| #82697 | 115 kV | IMPERIAL IRRIGATION DISTRICT | IN SERVICE | 1.6 mi |
| #81499 | 115 kV | SOUTHERN CALIFORNIA EDISON | IN SERVICE | 3.2 mi |
| #88478 | 115 kV | SOUTHERN CALIFORNIA EDISON | IN SERVICE | 4.4 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of MIRAGE, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| DEVERS | Substation-Adjacent | CA | Riverside County | 500 kV | 1,000 MW | 5.7 yrs | 63.7 |
| UNKNOWN307724 | Substation-Adjacent | CA | Riverside County | 230 kV | 300 MW | 5.7 yrs | 57.0 |
| Greenfield (DEVERS - VALLEY) | Greenfield | CA | Riverside County | 500 kV | 1,000 MW | 5.7 yrs | 56.9 |
| Greenfield (RED BLUFF - DEVERS) | Greenfield | CA | Riverside County | 500 kV | 1,000 MW | 5.7 yrs | 56.7 |
| TAP307979 | Substation-Adjacent | CA | Riverside County | 115 kV | 100 MW | 5.7 yrs | 56.1 |
| VENWIND | Substation-Adjacent | CA | Riverside County | 230 kV | 300 MW | 5.7 yrs | 55.9 |
| CONCHO | Substation-Adjacent | CA | Riverside County | 115 kV | 100 MW | 5.7 yrs | 55.7 |
| TAP305309 | Substation-Adjacent | CA | Riverside County | 115 kV | 100 MW | 5.7 yrs | 55.5 |
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for MIRAGE substation, California. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.