TAP158563
SubstationAlaska · CHUGACH ELECTRIC ASSN INC
TAP158563 is an electric transmission substation in Alaska, operated by CHUGACH ELECTRIC ASSN INC. It is classified as sub-transmission (138 kv) and connects 1 transmission line. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #61381 | 138 kV | CHUGACH ELECTRIC ASSN INC | IN SERVICE | 1.1 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of TAP158563, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| International | Brownfield | AK | Anchorage Municipality | — | 46 MW | — | 67.4 |
| TAP158536 | Substation-Adjacent | AK | Anchorage Municipality | 230 kV | 300 MW | 3.5 yrs | 65.6 |
| RISER158537 | Substation-Adjacent | AK | Anchorage Municipality | 230 kV | 300 MW | 3.5 yrs | 65.5 |
| UNIVERSITY | Substation-Adjacent | AK | Anchorage Municipality | 230 kV | 300 MW | 3.5 yrs | 65.4 |
| PT. MACKENZIE | Substation-Adjacent | AK | Anchorage Municipality | 230 kV | 300 MW | 3.5 yrs | 65.1 |
| RISER158451 | Substation-Adjacent | AK | Anchorage Municipality | 230 kV | 300 MW | 3.5 yrs | 64.5 |
| ANCHORAGE 1 | Substation-Adjacent | AK | Anchorage Municipality | 115 kV | 100 MW | 3.5 yrs | 62.6 |
| UNKNOWN158561 | Substation-Adjacent | AK | Anchorage Municipality | 138 kV | 100 MW | 3.5 yrs | 62.5 |
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for TAP158563 substation, Alaska. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.