Meta Henrico Data Center
DatacenteractiveVA · Meta
Meta Henrico Data Center is an operating datacenter facility in VA, operated by Meta.. Existing datacenter clusters are a strong signal for new development: they confirm power availability, fiber peering, and a permitting precedent — which is why nearby candidate sites often inherit the same speed-to-power advantages.
Facility
Nearby internet exchanges
- QTS Richmond (RIC1)Sandston, VA · 22 networks
- Pixel Factory Data CenterAshland, VA · 11 networks
- EdgeConneX Richmond (EDCRIC01)Richmond, VA · 3 networks
- Flexential - Richmond (RIC01/02)Richmond, VA · 1 networks
- Hosted Backbone Richmond1Richmond, VA · 0 networks
Other datacenters nearby
- Meta Henrico Data CenterMeta · VA
- QTS Richmond Data CenterQuality Technology Services · Sandston, VA
- Bank of America Data CenterVA
- Meta Henrico Data CenterMeta · VA
- Meta Henrico Data CenterMeta · VA
Nearby datacenter candidate sites
Scored candidate sites near Meta Henrico Data Center, ranked by DC Readiness — useful for evaluating expansion or second-site options in the same power/fiber market.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| ELMONT | Substation-Adjacent | VA | Hanover County | 500 kV | 1,000 MW | 3.1 yrs | 79.3 |
| Bellmeade Power Station | Brownfield | VA | Richmond | — | 330 MW | — | 77.5 |
| SPRUANCE NUG | Substation-Adjacent | VA | Richmond city | 230 kV | 300 MW | 3.1 yrs | 77.1 |
| TAP146366 | Substation-Adjacent | VA | Richmond city | 230 kV | 300 MW | 3.1 yrs | 76.4 |
| LAKESIDE | Substation-Adjacent | VA | Richmond city | 230 kV | 300 MW | 3.1 yrs | 75.7 |
| Greenfield (ELMONT - CHICKAHOMINY) | Greenfield | VA | Henrico County | 500 kV | 1,000 MW | 3.1 yrs | 75.3 |
| PLAZA | Substation-Adjacent | VA | Richmond city | 230 kV | 300 MW | 3.1 yrs | 75.3 |
| CHESTERFIELD | Substation-Adjacent | VA | Henrico County | 230 kV | 300 MW | 3.1 yrs | 75.0 |
Dataset updated . Screening estimates derived from public data sources.
Datacenter records are derived from public facility datasets (PNNL and related sources) and may be incomplete or lag operational changes. Capacity and footprint are catalogued estimates — confirm operator, capacity, and availability directly with the facility.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Meta Henrico Data Center, VA. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.