UNKNOWN209315

Substation-Adjacent

Campbell County, Wyoming · WECC

DC Readiness
59.2
Good / 100

UNKNOWN209315 is a substation-adjacent datacenter candidate site in Campbell County, Wyoming, interconnecting through WECC. It screens at 59.2/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN209315
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPACT Gillette
IXP distance23.6 mi
Fiber providers6
Fiber coverage43.2%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance391.5 mi

Site characteristics

Parcel ownerPOWDER RIVER ENERGY CORPORATION
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous

Risk & environment

Flood zoneZone X
Water stress (WRI)2.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score90/100
Construction cost index94.7 (avg 100)

Location context

Nearest datacenterDatacenter 1414729942
DC distance20.9 mi
Nearest rail7.4 mi
Nearest gas pipeline2.7 mi
Nearest fiber route208.3 mi
County hazard (FEMA NRI)Very Low (10)
DC tax incentiveYes (no_income_tax)
Commercial electricity9.23¢/kWh
Industrial electricity7.25¢/kWh
Cooling degree days300
Heating degree days7,600
Land price / acre$959

Incentive detail: No state corporate or personal income tax; low property taxes.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
31
Fiber connectivity12%
24
Energy cost10%
94
Water risk8%
48
Natural hazard8%
90
Buildability7%
80
Labor market4%
50
DC cluster4%
60
Land / acreage3%
69
Construction cost3%
71
Gas pipeline2%
91
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Campbell County, ranked by DC Readiness.

Sites near UNKNOWN209315
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN201359Substation-Adjacent230 kV300 MW1.7 yrs72.3
UNKNOWN201476Substation-Adjacent230 kV300 MW1.7 yrs72.1
WYODAKSubstation-Adjacent230 kV300 MW1.7 yrs70.9
HUGHESSubstation-Adjacent230 kV300 MW1.7 yrs69.5
RENOSubstation-Adjacent230 kV300 MW1.7 yrs68.6
UNKNOWN205619Substation-Adjacent115 kV100 MW1.7 yrs68.3
UNKNOWN205624Substation-Adjacent115 kV100 MW1.7 yrs68.3
UNKNOWN201475Substation-Adjacent230 kV300 MW1.7 yrs68.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN209315, Campbell County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.